Host partner presentation · H-03
You have read the proposal. The heat, the boundary and the payment are settled. This is what happens on your site once you say yes: what we survey, what lands on the slab, what your team has to do during construction, and how it runs for the next fifteen years.

Before anything is signed
Everything below starts from your metered demand rather than from our standard drawing. The thing that goes wrong with heat offtake is a design built on an assumed load: a delivery grade the loop cannot take, a pipe route nobody walked, a tie in on a board with no spare capacity. The survey happens before anything is signed, so if your loop does not fit, that is the moment it surfaces.
01
02
03
If your loop does not fit the delivery grade, the survey is where that surfaces. That is the point of doing it before heads of terms rather than after.
The sequence
01
The largest reason a host says no is not the commercial terms. It is the picture of a building site inside a live plant: the crane over the process, the road closed for a month, the trades nobody vetted walking past the control room. There is no ground up construction here. The slab and the pipe run are the only civil works, and both are scoped against your shutdown calendar rather than ours.
Your permit to work regime governs everything inside your fence. Contractors are inducted to your standard, and the works are sequenced so no part of your process is taken down for our benefit.
Indicative works sequence from slab pour to first metered delivery. Duration and sequencing are set against your shutdown calendar and the survey, not against a standard programme.

02
Two connections touch your plant and each is a planned event with a written method statement. The electrical tie in is a single point at 480 VAC three phase behind your existing meter. The thermal tie in lands at the handover exchanger, and where the connection into your loop needs an isolation window, that window is yours to set.
Commissioning proves the chain before any heat is offered to your process. First delivery is a metered event you witness, and the settlement basis is exercised on real readings before the first invoice exists.
The two connection events that touch your plant, and the isolation window each requires. Everything else happens on the slab.
03
Day to day, the pod is a fenced compound inside your site that hums and takes nothing from you. Our staff attend on a maintenance regime and hold their own spares. Access is agreed at heads of terms rather than negotiated at the gate, your safety regime governs while they are inside your fence, and incident authority is named in writing rather than left to practice.
There is no new operating discipline for your team. Nobody on your payroll runs our plant, carries our alarms or holds our spares, and no part of our service level places an obligation on your process to keep running.
What sits on your site and what sits on ours, across access, alarms, spares, staffing and incident authority.

04
Fifteen years is a long time to be paid on a basis nobody explained. What is measured, where the meter sits, what arrives on the statement each month, and what happens when the two of us disagree about a reading.
Delivered heat is measured at the handover exchanger on EN 1434 and settled on a defined period. You pay in cents per kilowatt hour of heat actually delivered, so a week you take nothing is a week you owe nothing. The dispute route is written into the metering and billing schedule with a defined response, and the energy reuse figure is reported on DIN EN 50600-4-6 on the same statement rather than on a separate one.
05
The pod repeats on the same slab arrangement and the same exchanger boundary until your site is full, and each additional pod needs your written agreement to that increment. The exit is written the same way, because nobody gives up a footprint for fifteen years without knowing how it ends.

One thermal architecture runs the whole ladder, so nothing about the design changes between the first pod and the last one on your site. What changes is how many sit on the slab. Expansion is exercised against your capacity being confirmed deliverable, and that condition is written into the option rather than left to goodwill at the time.
One site visit, one NDA
Contact